Case Study: Anfield Roof Removal – Precision Lifting Under Pressure

Project Overview

Ainscough Crane Hire, the UK’s leading crane hire company, played a pivotal role in a critical phase of the Anfield Road Stand redevelopment: the complex and time-sensitive removal of the old roof from the preexisting structure. This high-profile project demanded exceptional planning, a vast array of lifting equipment, and seamless internal collaboration to meet the demanding schedule driven by the football season.

The Challenge: The removal of the old roof presented multiple significant challenges:

  • Time Sensitivity: With the football season dictating the timeline, Ainscough had a narrow two-week window to complete the entire operation. Crucially, access to the Anfield pitch was granted just days after the final home game of the season.
  • Logistical Complexity: The project required navigating a staggering 220 transport movements through a notoriously very tight tunnel to access the pitch, demanding meticulous planning and execution from the transport teams.
  • Sensitive Environment: Operating on a world-famous football pitch necessitated extreme care, requiring robust measures to protect the playing surface.
  • Heavy and Varied Lifts: The roof components were large and heavy, requiring a diverse range of crane capacities and types to handle different sections effectively.

Ainscough’s Collaborative Solution and Execution: Ainscough Crane Hire tackled this multifaceted challenge with a truly collaborative approach, leveraging expertise from across its national network:

  • Integrated Team Effort: The project was a testament to the synergy between Ainscough’s Regional, Transport, Small Cranes, and Heavy Cranes teams, ensuring every aspect of the operation was coordinated perfectly.
  • Extensive Fleet Deployment: A significant and diverse fleet of cranes was mobilised:
    • Two powerful crawler cranes (600t and 400t capacity) for the heaviest lifts.
    • A versatile 550t strut crane.
    • Five different mobile cranes of varying capacities, including two 300t units, a 200t, and a 100t crane, providing flexibility for various lifting requirements.
  • Unprecedented Pitch Protection: To safeguard the iconic Anfield pitch, all cranes operated on a specially laid matted surface, utilising 86 heavy-duty steel mats. This was noted as probably the largest collection of mats used at one location in Ainscough’s history, highlighting the scale of the protective measures.
  • Precision Logistics: The Transport team executed the 220 movements through the constricted tunnel with utmost precision, ensuring continuous flow of equipment and components without incident.

Impact and Outcome: Ainscough Crane Hire’s expert execution ensured the successful and timely removal of the old Anfield Road Stand roof:

  • Project Timeline Maintained: The entire operation was completed within the strict two-week deadline, allowing subsequent construction phases to proceed as planned and avoiding any disruption to the upcoming football season.
  • Pitch Integrity Preserved: The extensive matting system effectively protected the Anfield pitch, showcasing Ainscough’s commitment to site preservation and meticulous planning.
  • Complex Logistics Mastered: The successful navigation of 220 movements through the tight tunnel demonstrated Ainscough’s unparalleled logistical capabilities for challenging urban environments.
  • Collaborative Excellence: The project highlighted Ainscough’s ability to seamlessly integrate various internal teams for large-scale, complex operations, delivering a unified and efficient service.

Further Details

Conclusion: The Anfield Road Stand roof removal stands as a prime example of Ainscough Crane Hire’s capacity to deliver safe, precise, and time-critical lifting solutions for major infrastructure projects. By deploying a vast and diverse fleet, executing complex logistics, and fostering unparalleled internal collaboration, Ainscough once again proved why it remains the UK’s leading crane hire company, capable of handling even the most demanding projects under significant pressure.